  10-MGD Dantercepies 2

Mountain Station
Mountain Station

General information  
Place Sëlva 
resort Dolomiti Superski 
Region Trentino-South Tyrol 
Country   
Name of lift Dantercepies 2 
Type 10-MGD 
Lift manufacturer Leitner 
Year of construction 2013 
Commissioning date 12 / 2013 


Infos for handicapped persons
Sorry, no information available.

Characteristics
Project rescheduled due to mudslide on old route. New route with middle station.

Summer 2022: 2 completely new drive groups. The DC motors and gearboxes were replaced by the Leitner Direct Drive

geometric data  
Height of valley station 2160 m
Height of mountain station 2291 m
Vertical rise 131 m
Route distance 498,21 m
Horizontal length ?? m
Average incline 27,8 %
Largest incline ?? %
Number of pillars 5 Stk
Greatest spanwidth ?? m
Max ground clearance ?? m
Trackwidth drive ?? m
Trackwidth line ?? m
Trackwidth return ?? m
Angle of wrap (drive wheel) ?? °
Drive altitude of site ?? m
Maximum capacity 3000 Pers/h
Travel time 1,5 min
Driving speed line 6 m/s
Driving speed station ?? m/s

electrical data  
Electrical control Leitner 
Remote control and telemonitoring system Leitner 
Power control system Leitner 
Number of drive 1 Stk
Drive power (Start) ?? kW
Drive power (Operation) 360 kW
Brake power ?? kW
Continuous brake power ?? kW
Driving station Valley station 
Drive type electrical 
Traction of drive direct drive 
Emergency drive diesel engine 
Traction of emergency drive hydrostatic 

cabins data  
Grip type LPA-M 
Cab manufacturer Sigma 
Cab model DIAMOND - C10D210 
Seating leather 
Seat heater no 
Heater no 
Aircon no 
Persons per cab 10 
Number of cabs 24 Stk
Cab distance 72 m
Cab interval 12 s
Garage type underground 
Garage place valley station 
Garage direction forward 
Loading direction forward 


rope data  
Rope manufacturer ?? 
Length of haul rope ?? m
Total weight of haul rope ?? t
Haul rope diameter 46 mm
Nominal strength of haul rope ?? N/mm²
Breaking strength of rope ?? kN
Tensionstation haulrope Mountain station 
Tension type hydraulical (controlled) 
Tension way 4 m

miscellaneous data  
Transport uphill 100 %
Transport downhill 100 %
Drive direction left 
Construction costs ?? EUR
Currency (Construction costs) Euro 
Construction period 8 months
Seasontime ❄ ☀ all-season 
Evacuation ropeway no 
Integrated rescue system ?? 
Rope position control ?? 
Asset number (Trail map) 40 

This information are for members only visible!


Support
Wrong data or something is missing?
Support us!
Updates
Datas: 11.02.2025
PHOTOS: ??

Lift-Statistics
14245 visit(s) since 12.12.2013
Last visit 03.04.2025

LIFT-WORLD IDs
Lift-ID: 17111
Place-ID: 1663