  6-CLD/B Valachovka



General information  
Place Deštné v Orlických horách 
resort ?? 
Region Královehradecký kraj 
Country   
Name of lift Valachovka 
Type 6-CLD/B 
Lift manufacturer Leitner 
Year of construction 2024 
Commissioning date 10/01/25 
Second-hand lift. Formerly lift no. 87 


Infos for handicapped persons
Sorry, no information available.

Characteristics
Sorry, no information available.

geometric data  
Height of valley station 667 m
Height of mountain station 878 m
Vertical rise 211 m
Route distance 808 m
Horizontal length 780 m
Average incline ?? %
Largest incline ?? %
Number of pillars 10 Stk
Greatest spanwidth ?? m
Max ground clearance ?? m
Trackwidth drive ?? m
Trackwidth line ?? m
Trackwidth return ?? m
Angle of wrap (drive wheel) ?? °
Drive altitude of site ?? m
Maximum capacity 2600 (3200) Pers/h
Travel time 2,7 min
Driving speed line 5,0 m/s
Driving speed station ?? m/s

electrical data  
Electrical control ?? 
Remote control and telemonitoring system ?? 
Power control system ?? 
Number of drive 2 Stk
Drive power (Start) ?? kW
Drive power (Operation) ?? kW
Brake power ?? kW
Continuous brake power ?? kW
Driving station Valley station 
Drive type electrical 
Traction of drive electromechanical 
Emergency drive ?? 
Traction of emergency drive ?? 

cabins data  
Grip type ?? 
Cab manufacturer Leitner 
Cab model ?? 
Bubble colour blue 
Seating leather 
Seat heater no 
Persons per cab
Number of cabs 44 (54) Stk
Cab distance 42 (34) m
Cab interval 8,4 (6,)8 s
Garage type ground floor 
Garage place valley station 
Garage direction ?? 
Loading direction ?? 


rope data  
Rope manufacturer ?? 
Length of haul rope ?? m
Total weight of haul rope ?? t
Haul rope diameter 44 mm
Nominal strength of haul rope ?? N/mm²
Breaking strength of rope ?? kN
Tensionstation haulrope Mountain station 
Tension type hydraulical (controlled) 
Tension way ?? m

miscellaneous data  
Transport uphill 100 %
Transport downhill ?? %
Drive direction left 
Construction costs ?? CZK
Currency (Construction costs) Czech koruna 
Construction period 6 months
Seasontime winter 
Situation of entrance parallel 
Situation of exit parallel 
Loading carpet yes 
Evacuation ropeway no 
Integrated rescue system no 
Rope position control no 
Asset number (Trail map) ?? 

This information are for members only visible!


Support
Wrong data or something is missing?
Support us!
Updates
Datas: 11/01/25
PHOTOS: ??

Lift-Statistics
258 visit(s) since 18/09/23
Last visit 19/01/25

LIFT-WORLD IDs
Lift-ID: 24893
Place-ID: 1675

https://www.seilbahntechnik.net/en/lifts/24893/datas.htm