page Title Date PHOTOS
1)   Hopfgarten - Salvenbahn     1x 📷
2)   Disassembly of the mountain station:   27. April 2004  9x 📷
3)   Disassembly of the mountain station   27. April 2004  9x 📷
4)   Dissamply of the valley station   28. April 2004  5x 📷
5)   Valley station   10. / 11. May 2004  9x 📷
6)   Mountain station   10. / 11. May 2004  10x 📷
7)   New building of the valley station   End of May 2004  3x 📷
8)   New building of the mountain station   End of May 2004  4x 📷
9)   New mountain station   06/04/2004  4x 📷
10)   New line   06/07/2004  8x 📷
11)   Form works for pillar groundings   06/08/2004  5x 📷
12)   Concrete works on the mountain station   06/08/2004  7x 📷
13)   Concrete works on the valley station   08. / 09. June 2004  9x 📷
14)   Mountain station   06/15/2004  6x 📷
15)   Valley station   06/16/2004  5x 📷
16)   Assembly works near the mountain station   21 / 22. June 2004  13x 📷
17)   Form works on the mountain station   06/21/2004  7x 📷
18)   Concrete works on the mountain station   06/22/2004  12x 📷
19)   Valley station   06/27/2004  5x 📷
20)   Concrete works for the gondola depot   06/29/2004  5x 📷
21)   Pillar assembly with the truck crane   06/29/2004  24x 📷
22)   Pillar assembly with the helicopter   06/29/2004  20x 📷
23)   Concrete works for the gondola depot   Begin of July 2004  10x 📷
24)   Concrete works on the valley station   Begin of July 2004  6x 📷
25)   Earth- and Concrete works (Valley station)   07/14/2004  6x 📷
26)   Assembling of valley station begins   07/19/2004  4x 📷
27)   Assembling of ropeway technology (Valley station)   20. - 24. July 2004  18x 📷
28)   Ropeway technology (Valley station)   25. - 29. July 2004  5x 📷
29)   Concrete works on the valley station   28. / 29. July 2004  10x 📷
30)   Concrete works on the mountain station   26. July 2004  6x 📷
31)   Concrete works on the valley station   02. / 03. August 2004  7x 📷
32)   Assembling of ropeway technology (Mountain station)   02. - 05. August 2004  9x 📷
33)   Assembled ropeway technology (Mountain station)   07. August 2004  10x 📷
34)   Construction works at valley station   04. - 08. August 2004  11x 📷
35)   Assembling of pillars and station covering (Valley)   09. August 2004  6x 📷
36)   Assembling of ropeway technology (Mountain station)   08. - 10. August 2004  10x 📷
37)   Work on valley station   11. - 19. August 2004  12x 📷
38)   Assembling of ropeway technology (Mountain station)   17. August 2004  15x 📷
39)   Earthworks (Mountain station)   19. August 2004  5x 📷
40)   Valley and mountain station   22. August 2004  8x 📷
41)   Work on the valley station   23. August 2004  9x 📷
42)   Mountain station   23. August 2004  6x 📷
43)   The haul rope is supplied   23. / 24. August 2004  15x 📷
44)   Rope splicing   25. August 2004  10x 📷
45)   Electric - & miscellaneous works (Mountain station)   30. August 2004  9x 📷
46)   Cable installation   1. - 2. September 2004  15x 📷
47)   Roofing of valley station   2. - 8. September 2004  8x 📷
48)   (Mountain station)   13. September 2004  5x 📷
49)   First travel of the staff   22. September 2004  3x 📷
50)   Test run   15. October 2004  8x 📷